Optics

Channel-cut Si(111) + KB focusing mirrors

The main XALOC optical elements are: a diamond window (not shown in figure); a removable diamond filter (which could also be used as a Laue monochromator); a channel-cut monochromator; and a Kirkpatrick-Baez (KB) focusing system.

optical_layout2.jpg

 

 

 

 

 

 

 

 

 

 

 

 

 

20110325_OpticsGeneral 25 March 2011

The optics are completely assembled. Efforts are being directed to controls.

From left to right, XBPM+slits (blue), Horizontal Focusing Mirror (green), XBPM+slits (blue), Vertical Focusing Mirror (yellow), and the Monochromator (red) behind a temporary rack

 

Monochromator

Type Si(111) channel-cut, cryocooled
Gap between crystals        6 mm
Absorbed power  <100 W (in working conditions)
   460 W (in worst-case conditions)
 Bragg axis resolution (measured)  <1 urad (<0,2 arcsec)
 Bragg axis stability (measured)  <1 urad/1 hour

Status: Now operative. The Factory Acceptance Tests were done and approved in Summer 2008. The monochromator was installed at the beamline in 15-19 June 2009.

Monochromator in Factory Acceptance TestsXALOC_MonoCinel_01

Detail of the Silicon block. System controlling the pitch of the second crystal is shown above.

Black pieces are part of the interferometer used to evaluate the performance of the monochromator.

Cooling pipes are seen on the left, Bremsstrahlung block is shown on the right.XALOC_MonoCinel_02

 A typical error when commissioning channel-cut monochromators is to take a diffracted reflection which is not the designed one (e.g. Si442 instead of Si111). This error can be easily overcome, especially in the case of Si111, by varying the Bragg angle. Some info about this can be found here.

 

KB mirrors


Vertical Focusing Mirror       Horizontal Focusing mirror
 Type Elliptically bent mirror          Elliptically bent mirror
Substrate Si Si
Coating material   Si, Rh, Ir Si, Rh, Ir
Angle of incidence        4.1 mrad 4.1 mrad
Optical length  300 mm 600 mm
rms slope error (bent, measured)  <0,1 urad
 <0,1 urad
 Pitch stability (measured)  <4 urad/1 hour  N.A.

 

Status: Now operative. The Factory Acceptance Tests were done and approved in November-December 2008. The mirror vessels and positioning systems were installed at the beamline 9-13 June 2009. Mirrors were installed in Oct-Dec 2010.

 

Vertical focusing Mirror in Factory Tests

XALOC_VFMIrelec_01

Horizontal XALOC_HFMIrelec_01Focusing Mirror in Factory Tests

 

 Other Elements

Other optical elements are white beam attenuators, slits,  photon shutter, fluorescent screens and x-ray beam positioning monitors. All these elements have been installed.

 

 

 

 